Chinese Landscape Painting #2

The first time I noticed something was about to happen was when I saw two white-on-blue signs amongst the rows of vegetables (looking west, below), asking the growers to harvest them befofre the end of the month as “works” were going to commence for this bank of the river. Works commenced two months later.
Early January 2024


This guerilla growing of vegetables on any underused land is quite common as many people rehoused in high-rises just missi growing vegetables. Any patch of underused land can be appropriated in this way. I’ve seen curbside patches as small as half a square meter used for growing spring onions.



19 March 2024: Chinese landscape painting likes a blank canvas on which to begin. The first step is to get an excavator onsite to demolish any illegal structures and dig up any illegal concrete and vegetables.

20 March 2024: It’s not wonton destruction, The excavator operator uproots any trees to be retained so the gardeners can bind their root stocks before replanting the trees out of the way along the rear boundary of the site.

4 April 2024: The excavator offloads and places 1/2 inch thick steel plates and lays and overlaps them to form a stable base for the excavator to work on the embankments. I’m in awe of how adept the excavator operators are at moving these huge and heavy sheets of steel plate from one place to another. There’s a post expressing my admiration.1 While this is all taking place, the waterway is dammed at each end and the water level lowered to make the banks more accessible and allow the embankment rebuilding to begin. It’s messy business.




6 April 2024: Some chickens find it difficult to keep away from their usual patch. Herons come to check out new opportunities. That night, more rocks were delivered.


7 April 2024: April 2024 was a busy month. The waterway is dammed and the water level lowered by one metre. The construction road of steel plates has been made. Concrete pegs that will form the sub-foundation for the embankment walls have been delivered. It doesn’t take much driving to be driven into the mud. A 30cm layer of concrete is then poured over them to form the foundation for the new embankment walls. Truckloads of boulders were delivered overnight. The stoneworkers get to work. I have a lot of respect for these guys. They know instinctively what to do and how to do it. This of course is a problem if you’d like them to do anything other than what they know how to do, but for situations like this it goes very smoothly. I never saw anybody consulting a drawing or holding a clipboard. In this context it’s okay, for a building project maybe not.






This sequence of excavation, piling, making the slab and building the walls and backfilling them with rock, proceeds up the waterway.



11 April 2024: The banks get tidied up and the sludge hauled away at night. Before these trucks leave the site, their wheels will be thoroughly hosed down so they don’t track mud onto the road. At the right end of the photo below is a red crane and on the bank below it is (I found out later) some kind of spacing template.

13 April 2024: There’s many things happening on the site at the same time.The red crane is there to drive concrete piles into the riverbank. They’re friction piles but the drop very quickly into the mud and only need the slightest of nudges to be placed in position. I don’t know by what mechanism the operator can pick up these piles by one end.



15 April 2025: The river water level is now about 1.5 metres lower and the depth about 50cm midstream. It’s not pretty. The water always brownish because of suspended clay from upstream. Some chickens find it difficult to keep away from their usual patch. Herons come to check out what new opportunities in this new wasteland.


Government Objective: Clean and non-silting river with no direct discharge of sewge, unimpeded flor of wter, intact river embankment and no damabged afforestation or illegal construction along the river shoreline.


It’s possible for an operator to make an excavator step up and down a muddy bank. Here, the operator is taking a plate and placing it a level lower to make a platform to reverse onto while using the bucket to stabilize the excavator. Theoretically, they could do this any number of times, making the next platform as it goes up or down. It’s always a pleasure to watch someone who’s good at what they do. The reason for this action was to retrieve and repair the floating pump that had been keeping the water level low.
The wall construction looks simple but it starts off as drywalling with only small gaps between the rocks. Boulders are trucked in overnight and left at the next section of wall. The masons split the rocks and set them in place, leaving any unused rock as backfill over which concrete will be poured to stabilize the wall. The middle photo shows a vertical gap where the piece of white board is but I don’t know what it’s for.



16 May – 8 June 2024: The concrete friction piles turn out to be supports for a concrete slab that I hear is to become a stop for a new water taxi service that’s rumoured to extend as far as the site of the Wenzhou International Horticultural Expo due to open in April next year. A little bit downstream the same construction is used for a small fishing platform.
9 July 2024: Upstream the work on the taxi stop continues while downstream, large boulders are placed on top of the stone wall that has now been backfilled, with rubble and concrete and a 10-15cm layer of soil placed ready to receive plants. An extraordinary floating excavator demolishes the temporary dam and the waterway returns to its natural level. It then proceeds to dredge the waterway.


15 July 2024: The rock walling changes to a concrete retaining wall at the concrete platform for the water taxi stop that has short bridges connecting it to the bank. Sheet piles are driven to facilitate the construction of this concrete retaining wall. In the rightmost photograph, you’ll notice the perimeter fence of the neighbouring tower block community has been part dismantled and part demolished to temporarily appropriate construction space.




The river water looks extremely murky but (yesterday) I saw a man proudly holding a 30cm fish of some kind. The shape, size and colour were like those of the fish touching the leftmost squid on the counter below. Fish names in other languages are always difficult. I always point to the one I want and my fishmonger will always gesture to ask if I want it gutted and descaled. We should eat more fish.

16 August 2024: Then come the boulders. I’m not sure what they do, but this isn’t the only place around town I’ve seen them. The wall seems solid enough to not need them but they could function as some kind of railing to stop toddlers making a dash for the edge. (Later, when plants are grown around and over them, it doesn’t look bad.) Here, the excavator operator is using that ditch behind the fishing platform to mix the cement used to bed the boulders.



13 October 2024: Nothing has changed since August and there’s nobody around. I don’t think it’s a seasonal thing as workers have been working all summer and it’s not that much cooler in October. The name of this city is Wenzhou (温州) which means “warm place”. I think the absence of work might have something to do with the budget being allocated in phases determined by calendar month instead of by completed work stages. This view is looking south and the sun has just risen but already on the bridge to the west there’s a one-off street market being set up for food, fish, clothing, household products …


27 October 2024: A few days later, sizeable trees begin to be hauled in while, at the other end of the site, work beganon some stairs linking the embankment with the footpath above. Under the bridge, there is already a pathway that functions as a pedestrian crossing to the embankment on the other side.




27 November 2024 – 18January 2025: Once again, there was a strange two-month gap in works. The wall is rebuilt, the ground is shaped into that for planting and that for pathways, and planting begins. Newly planted trees are propped up with three pieces of wood wired together at the top and usually painted yellow, although I have seen green ones and, less occasionally pale blue ones. These props are typically kept in place for the first six months after replanting. For special or delicate trees, bags of liquid nutrients are suspended from the propes and fed by tube into the rootstock.




By mid-January, it’s all beginning to take shape. Paths have been completed and edging is progressing. Work begins on the railings for the platforms and where the path is close to the water. Once again, there is a strange two-month gap in works.



By mid-January, it’s all beginning to take shape. Paths have been completed and their edging is progressing. Work begins on the railings for the platforms and for where the path is close to the water.
13 April 2025: The wall for the upper platform down to the embankment and the ferry landing was completed before I even knew about it.


24 April 2025: The earthworks excavator has gone and a lighter, more manouvrable one is brought in for detail work such digging holes for tree planting, spreading topsoil conveyed to it by a smaller, rubber-wheeled excavator, and for positioning the trees.



24 April 2025: The earthworks excavator has gone and a lighter, more manoeuvrable one is brought in for detail work such digging holes for tree planting, spreading topsoil conveyed to it by a smaller, rubber-wheeled excavator, and for positioning the trees. In the third image below, white lines have been chalked on the ground to mark planting divisions in the groundcover. This is very characteristic of this type of Chinese landscaping. You will see it on sides of roads as well as in tower community landscaping.



4 May 2025: Groundcover planting is imminent.

Once groundcover planting begins, it is finished in what seems like no time at all. In this case, about two days and all the topsoil is planted. Teams of workers, usually women, worked solidly and methodically for two days. And then they were gone, presumably to some different site to do the same thing. These workers might be managed by an agency but it’s more likely there’s an app that lets them choose where and when they want to work.
30 May 2025: The ground covering is complete and all that remains is the upper platform that will be the main entrance to the ferry stop.


31 May 2025: The ferry landing and the fishing platform are covered in wood-effect decking and pieces of timber are affixed to each of the railing posts, making them look less metallic The handrailing is wood, varnished. The upper platform and its steps are to be clad in stone.


8 January 2025: It took two years start to finish, with two or perhaps three two-month intermissions so that’s a year and a half of continuous work. but at varying intensity. For the first six months there was just a single excavator operator preparing the site. After that came building the embankment walls which required a team of five or size to create the formwork for the wall foundation slab. There were maybe 30 people for the two days in May when the groundcover planting took place. This is the biggest difference between the two sides. Although the south side has a newly built platform for fishing, yesterday I saw a person fishing on the north bank because it was sunnier and the temperature was about 10°C. Because the south bank links to the bridges and roads at each end, it is the more used – as you’d expect from something created as a piece of transportation infrastructure. It will always be the more public bank. About 7am, two people practice tai-chi where the south bank path widens to change direction. I’d like to join them and would probably be welcome but I hesitate as they look like they’ve been doing tai-chi for as many decades as I have weeks.
• • •